Redpath Deilmann GmbH

  • Redpath Deilmann: sinking work completed

    Since 2018, Redpath Deilmann GmbH, Dortmund/Germany, has been sinking two shafts for the new Nezhinskiy potash mine in Belarus on behalf of Slavkaliy IOOO (Figure 1). The sinking crews completed their work on 17th July 2020. Both shafts were sunk using shaft boring roadheaders (SBR) from Herrenknecht. The total construction time was 581 days.

    Key Figures of the construction period:

    • 697 m shaft constructed;
    • 3,225 tubbings fitted;
    • 55,714 m3 of soil excavated;
    • 14,165 m3 of concrete installed;
    • two shaft landings fitted; and
    • 20,394 working hours completed without a single accident.

    (Redpath Deilmann/Si.)

  • Company marks a new milestone with another shaft sinking record in Belarus

    In 2018 Redpath Deilmann (formerly Deilmann-Haniel), Dortmund/Germany, commenced work on a contract from Slavkaliy IOOO to construct two surface shafts for the new Nezhinsky potash mine in the Republic of Belarus. The project remit is to sink two 8.0 m diameter freeze shafts to a depth of some 700 m, this to be a fully-mechanised operation based around shaft boring roadheaders (SBR), rather than the conventional drilling and firing.

    After completion of the foreshafts needed to set up the shaft boring machines the real sinking work with the two SBRs was able to commence in shaft number 2 in December 2018 followed by shaft number 1 in January 2019. The SBR machines were designed and built by Herrenknecht AG in Schwanau in close cooperation with Redpath Deilmann, also based in Germany. With some fine-tuning occasionally applied by the site crew to both the machines and the operating procedures the high-performing technology was soon interacting with an efficient workflow routine to the effect that by May 2019, and in spite of difficult geological conditions, the project set a new Belarusian shaft sinking record for metres sunk per month. The actual figures were 88 m and 83 m of bored shaft respectively.

    Sinking work was then temporarily halted in the summer and autumn of 2019 so that 215 tubbing rings could be installed in both shafts, the rock wall behind being sealed by injection. The sinking work was then resumed and in March 2020 the first salt formations were reached at a depth of nearly 500 m. The improved geological conditions, combined with a great team effort on the part of the construction crew, saw the Belarusian sinking record broken for a second time in April 2020. And on top of this, the 144.4 m of completed shaft easily exceeded the existing Redpath Deilmann record that had stood for nearly 100 years – thereby marking another famous milestone in the company’s history (Figure 1). Both shafts have now reached the first planned inset levels – at a depth of about 670 m – and the next stage of the operation will involve the excavation and support of the landings.

    The entire project is scheduled for delivery by mid-2022. After the shaft operations have been completed, which will include the construction and installation of the various insets, skip pockets, bunkers and guide fittings, there will still be several kilometres of underground roadway to be excavated in line with the contractual agreement. Finally, the surface installations can then be dismantled and the site handed back to Slavkaliy.

    It is still too early to tell how the current SARS-CoV-2 epidemic will affect the work at the shaft site. As well as a large number of Belarusian and Russian staff the project also includes some 50 engineers and supervisors from the German parent company. The measures to be taken in order to prevent the spread of this new corona virus are being clearly communicated and everyone knows what has to be done to protect himself. The German personnel on site has shown great commitment with its continued support for the ongoing operations, notwithstanding the restricted opportunities available at present for returning home. In spite of the corona situation the project team therefore remains fully manned and all involved are as healthy and motivated as they were on day one. (REDPATH DEILMANN/Si.)

  • Name Change of Deilmann-Haniel GmbH Dortmund

    In 2012, all special mining activities of the former Deilmann-Haniel International were restructured and bundled under the roof of the Redpath Group based in North Bay, Ontario/Canada. As a result, Deilmann-Haniel became a 100 % subsidiary of Redpath Mining Inc. which is a wholly-owned subsidiary of ATON GmbH based in Munich/Germany. Since 2012, the affiliation to the Redpath Group was documented by adding “Member of the Redpath Group” to the Deilmann-Haniel company name.

    After seven years now as member of the Redpath Group Deilmann-Haniel would like to bear the name of the world’s leading company in the field of “Mining Construction“ even directly in its name, and would like to preserve the more than 130 years of tradition of success of the “Deilmanner” at the same time. That’s why Deilmann-Haniel has renamed the company effective 1st October 2019 into REDPATH DEILMANN GmbH and will adopt the logo of the group as well as all other companies of the Redpath Group.

    The new company name shows to all clients, partners, suppliers, and other stakeholders that the company is part of the world’s leading mining contracting group, which stands for satey, quality, reliability, innovation and efficiency. All other company data such as address, commercial register number, account data or VAT ID remain unchanged. The web address is www.redpathdeilmann.com since October 2019. (REDPATH DEILMANN/Si.)